Why use a two-stage cementing operation?
In complex wellbore environments, a single cementing stage may not provide adequate zonal isolation or well integrity. That’s where two-stage cementing comes in an approach designed to optimize placement and isolation across multiple intervals.
This guide walks you through:
- Cementing objectives
- Volume & sack calculations
- Placement planning
- Field verification
⚙️ What Is Two-Stage Cementing?
A two-stage cementing operation involves placing two cement plugs sequentially:
-
Primary Stage – Isolates the lower section and provides initial casing support.
-
Secondary Stage – Isolates the upper zones and completes the seal.
This technique is essential in:
- Long casing strings
- Deep wells with weak formations
- Wells requiring selective zonal isolation
📐 Step-by-Step: Cementing Volume Calculations
🔹 1. Cementing Objectives
- Primary Stage: Zonal isolation and casing support in lower sections
- Secondary Stage: Final isolation of upper zones and shallow formations
🔹 2. Cement Volume Calculations
🧮 2.1 Primary Stage
Annular Volume
To fill the annular space between the casing and borehole:
Casing Volume
To calculate internal displacement inside the casing:
Total Cement Volume
Number of Sacks
🧮 2.2 Secondary Stage
Repeat the same calculation steps for the secondary section:
- Secondary Annular Volume
- Secondary Casing Volume
- Total Cement Volume (with excess)
- Number of Sacks
🔄 Example Calculation
✅ Primary Cementing Stage
Parameter | Value |
---|---|
Slurry Yield | 1.15 bbl/sack |
Annular Volume | 150 bbl |
Casing Volume | 50 bbl |
Excess Volume (15%) | 22.5 bbl |
Total Volume | 222.5 bbl |
Number of Sacks | ≈ 193 sacks |
✅ Secondary Cementing Stage
Parameter | Value |
---|---|
Slurry Yield | 1.20 bbl/sack |
Annular Volume | 200 bbl |
Casing Volume | 70 bbl |
Excess Volume (20%) | 40 bbl |
Total Volume | 310 bbl |
Number of Sacks | ≈ 258 sacks |
🚧 Cement Placement Procedure
🔹 Primary Stage
- Pump cement slurry
- Displace with spacer fluid
- Monitor real-time returns
- Allow cement to set and cure before proceeding
🔹 Secondary Stage
- Open stage tool
- Pump secondary slurry
- Displace and shut in
- Monitor pressure and placement
🧪 Verification & Monitoring
- Cement Bond Log (CBL): Run after both stages to assess cement-to-casing and cement-to-formation bond.
- Log Analysis: Confirm zonal isolation and mechanical support. Adjust if logs indicate poor bonding or channeling.
✅ Final Thoughts
A two-stage cementing job is all about precision, planning, and verification. It enables better zonal isolation in extended or challenging well sections where single-stage cementing would fall short.
By following a systematic approach to volume calculations and monitoring, engineers can:
- Avoid remedial cementing
- Improve well integrity
- Reduce NPT and operational costs